OVERVIEW OF NHON TRACH INDUSTRIAL PARK PROJECT 1
Investor: IDICO Urban and Industrial Park Development Company Limited (IDICO-URBIZ) – Prestigious industrial park investor in Vietnam
Industrial Park Address: Nhon Trach District – Dong Nai Province
Total area: 448.5 hectares
Construction investment situation: Completion of investment in construction of the industrial park technical infrastructure system.
Investment attraction situation: 100% of industrial land area has been leased.
Operation time: 1998- 2048
Image of the entrance gate to Nhon Trach 1 Industrial Park
LOCATION OF NHON TRACH 1 INDUSTRIAL PARK
Nhon Trach 1 Industrial Park in Nhon Trach new urban area is located in the planning of an industrial city with a scale of 8,000 hectares, including a system of airports, ports, industrial parks, residential planning areas, and entertainment areas. intellectual…
Convenient transportation by road, waterway, air, and industrial park
- City. Ho Chi Minh 45km,
- City. Bien Hoa 40km,
- City. Vung Tau 60km…
The area has a temperate climate (20-30oC), no storms and earthquakes, high soil load bearing intensity (1.5-2.5kg/cm2), so it saves costs and is convenient for construction implementation. Build a production factory.
Currently, the Industrial Park has been chosen by many investors from Korea, Taiwan, Switzerland, Malaysia, France, America… to invest in developing manufacturing factories..
Image of Nhon Trach 1 Industrial Park project location
INFRASTRUCTURE OF NHON TRACH INDUSTRIAL PARK 1
Power supply:
- Power supply: The industrial park is supplied with power from Tuy Ha 110/22KV Transformer Station, capacity of 182MVA managed and operated by IDICO Housing and Urban Development Investment Joint Stock Company (IDICO-UDICO). Tuy Ha 110kV transformer station is connected and supplies 110kV power from the National Power System through Long Binh 220/110kV transformer station with a stable power source, ensuring quality. – Voltage supply to factories : 22kV
- 22kV electricity unit price does not include VAT (according to State regulations, Decision 648/QD-BCT dated March 20, 2019):
+ Normal hours: 1,555VND/kWh
+ Peak hour: 2,871VND/kWh
+ Off-peak hours: 1,007VND/kWh
Image of power supply station in Nhon Trach 1 Industrial Park
Water supply:
- Water supply source: Factories in the Industrial Park are supplied with water from Tuy Ha underground water plant with a capacity of 22,000m3/day and night provided by Investor IDICO-URBIZ.
- Water price according to regulations of Dong Nai province.
Communications:
- The communication system is provided by network operators such as: VNPT, FPT, Viettel… ensuring smooth domestic and international communication. Includes full range of services such as: telephone, mobile phone, Fax, Internet…
Drainage:
- Including: The rainwater drainage system and wastewater drainage system are planned and built separately, running along internal roads to ensure the collection of all rainwater and wastewater from factories in the industrial park.
- Rainwater is drained directly into the receiving source.
- Wastewater is collected to the centralized wastewater treatment station of the industrial park and thoroughly treated, meeting required standards before being discharged into the environment.
Image of drainage system installation at Nhon Trach 1 Industrial Park
Wastewater treatment:
The centralized wastewater treatment plant located in Nhon Trach 1 industrial park has a treatment capacity of 6,000m3/day and night. Currently, IDICO-URBIZ is implementing investment procedures to renovate and upgrade the wastewater treatment plant to 10,000m3/day and night.
Image of the wastewater treatment plant of Nhon Trach Industrial Park taken from above
Traffic inside and outside the Industrial Park:
- Road: Nhon Trach 1 Industrial Park is located in the center of the southern key economic region including Ho Chi Minh City – Bien Hoa – Vung Tau, convenient for road and waterway transportation.
- The road system includes: Road 25B connecting with National Highway 51 to City. Ho Chi Minh (50km), go to Bien Hoa (40km), go to City. Vung Tau (60km)
* Waterway:
Nhon Trach Industrial Park 1 way:
- Saigon Port 48 km.
- Vung Tau Port 60km.
- Go Dau Port 15km
Infrastructure of Nhon Trach 1 Industrial Park
Utilities
- Nhon Trach Industrial Park Police Station:
Address: Tran Phu, Phuoc Thien, Nhon Trach, Dong Nai
Phone: 0251 3569 700
- Nhon Trach Industrial Park Police Station, supporting security and order work in the Industrial Park Area
Nhon Trach Fire Prevention Police Department
Address: Street No. 2, Phuoc Thien, Nhon Trach, Dong Nai
Phone: 0251 3569 696
- Nhon Trach Fire Prevention Police Department, supporting fire protection and security work in the Industrial Park Area
INDUSTRIES THAT ATTRACT INVESTMENT IN NHON TRACH 1 INDUSTRIAL PARK
- Mechanical production and processing of machinery, equipment, iron and steel;
- Production of construction materials, production and repair of motorbikes and equipment;
- Power electronics;
- Production and processing of leather shoes and garments;
- Processing industrial and food products;
INVESTMENT INCENTIVES
- Corporate income tax rate: 20%
- Tax incentives:
Preferential tax rate is 17% for 10 consecutive years from the first year the enterprise has revenue from the project. When this preferential tax rate expires, businesses will switch to applying the 20% tax rate.
- Tax exemption for 2 years and 50% reduction for the next 4 years from the date of taxable income
- Import tax: Enterprises are exempt from import tax on imported goods according to the provisions of Article 16 of the Law on Export Tax and Import Tax No. 45/2005/QH11 dated June 14, 2005 and Article 12 of Decree No. 87 /2010/ND-CP dated August 13, 2010 of the Government detailing the implementation of a number of điều của Luật Thuế xuất khẩu, Thuế nhập khẩu.
INVESTMENT PROCEDURES IN NHON TRACH 1 INDUSTRIAL PARK
1.Investors learn about industrial park information and land sublease conditions with IDICO.
2. Agree on conditions to sign a Memorandum of Land Sublease with IDICO:
- Remember, land sublease is valid for 4 months;
- Pay a deposit to keep the land equivalent to 10,000 USD/ha. The deposit will be deducted from payments under the official Land Sublease Contract;
- During the 4-month period of the Land Sublease Memorandum, the investor will carry out procedures to be granted an Investment Certificate; Establish a Project business to be able to sign a Contract with IDICO.
3.Procedures to be carried out:
3.1. Carry out procedures for investment policy approval with the Investment Registration Authority (Time 15-30 days).
3.2. After receiving approval for the investment policy, the Investor continues to carry out the procedure for granting the Investment Registration Certificate (Duration is about 15 days);
3.3. At the same time, carry out procedures for preparing and applying for approval of the Environmental Impact Assessment Report at the EIA Appraisal and Approval Agency (Time about 60-90 days).
3.4. After obtaining the Investment Registration Certificate, the Investor carries out procedures to establish a Project Enterprise (Time within ~3 days)
3.5. Within 30 days from the date of issuance of the Investment Certificate, the Investor signs a Land Sublease Contract with IDICO.
3.6. Carry out procedures for granting a Construction Permit:
- After the Investor signs the Land Sublease Contract; At the same time, the Project’s Environmental Impact Assessment Report was approved; The design is approved for fire protection, the investor carries out the procedures for applying for a construction permit.
- After being granted the Construction License, the Investor will proceed with project construction.